Owner: LTV Steel Cleveland, Ohio
Project Duration: 1996 - 1998
Final Cost Estimate: $15 million
|
|
|
|
PROJECT DESCRIPTION
R.E. Warner & Associates, Inc. selected and installed equipment for sidetrimming, splitting and inspecting 84" coils at LTV Steel Companys No. 1 Finishing Department in Cleveland, Ohio.
R.E. Warner & Associates, Inc. completed preliminary and final engineering for the installation of equipment for this sidetrimmer/splitter project.
|
|
|
 |
|
|
R.E. Warner & Associates, Inc. provided preliminary layouts, cost development, bid specifications and site selection for the preliminary phase. R.E. Warner & Associates, Inc. provided structural and foundation design (augercast piles) for equipment support, mechanical piping and electrical engineering for complete installation of equipment. R.E. Warner & Associates, Inc. designed inspection lighting booth for improved quality control of product. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|