As part of a consultant team, R.E. Warner provided electrical engineering services to perform a field survey and prepare plans and specifications to replace low voltage equipment at NEORSD’s Southerly Wastewater Treatment Plant. Our scope of work includes the following:

  • Locate all identified panels, switchboards, drawout switchgear and Eddy Current Drive panels in the field and record
  • Prepare Basis of Design Report
  • Prepare Construction Cost Estimate for replacement of equipment
  • Prepare panelboard wiring and directory drawings for all equipment
  • Prepare specifications for purchase of replacement equipment
  • Prepare drawings showing location of all equipment to be replaced
  • Correct code violations that are discovered