As part of a consultant team, R.E. Warner provided electrical engineering services to perform a field survey and prepare plans and specifications to replace low voltage equipment at NEORSD’s Southerly Wastewater Treatment Plant. Our scope of work includes the following:
- Locate all identified panels, switchboards, drawout switchgear and Eddy Current Drive panels in the field and record
- Prepare Basis of Design Report
- Prepare Construction Cost Estimate for replacement of equipment
- Prepare panelboard wiring and directory drawings for all equipment
- Prepare specifications for purchase of replacement equipment
- Prepare drawings showing location of all equipment to be replaced
- Correct code violations that are discovered